How-To

Modular Home Utility Hookups: Water, Power, Sewer

The six-step sequence for connecting a modular home to water, drainage and power: stub positions, who connects, testing, earthing and the commissioning record.

Shallow utility trench crossing a building plot with bundled conduit and a marked water service entering a modular building

Connecting a modular home to water, drainage and electricity is a six-step sequence, and the most expensive step is the first one, because it is the only step that must happen before the unit is built. Every service has an entry position designed into the structure of a factory-completed unit, and that position cannot be moved on site. Once the unit exists, the site has to be arranged around it. This page describes the sequence and the division of responsibility at each step. It does not repeat our installation cost page, which treats connection as a cost head, nor our water supply planning page for the Philippine market, which covers supply sourcing and storage rather than the connection sequence. Compliance documentation is covered on our certification page, and the vocabulary follows our modular terminology guide. This page deliberately gives no voltage, frequency, pipe diameter or protective device ratings as fact, because those are determined by the supply available at the plot and by the applicable standard in the destination. Requirements may vary by application, market and applicable standard.

Step One: Agree the Stub Locations Before the Unit Ships

The unit has fixed entry and exit positions for water, waste and electrical supply. The site works have to be designed around them, which means they have to be known while the site is still being designed.

  • Obtain the interface drawing from the factory, showing every service entry position, its height above or below the finished floor level, and its required clearance.
  • Reconcile it with the substructure drawing produced by the locally licensed engineer. Penetrations through a slab or a wall are structural items and are not added afterwards.
  • Confirm the external approach route each service takes to reach its entry point, so that a trench does not cross a pier or conflict with another service.
  • Agree the position in writing between the factory, the site contractor and the buyer, and hold that drawing as the reference for the rest of the sequence.

Where a buyer changes the layout or the orientation after this drawing is agreed, the entry positions move with it, and the site works already designed for the old positions are wasted. This is the single most common cause of avoidable rework on a modular connection, and it originates months before delivery.

Step Two: Decide Who Provides the Connection on Site

Three parties can hold this scope, and the default allocation differs between markets. It must be explicit in the contract rather than assumed, because an unallocated scope becomes an argument at the moment it is needed.

  • The utility or the licensed contractor it requires. In many markets the connection to the public supply can only be made by the utility or by a contractor it has approved. That work is outside any building supplier's scope by definition.
  • The site contractor. Normally holds the external trenching, the ducts and the stub brought up to the building, and the connection from the stub into the building.
  • The factory or its commissioning technician. Some suppliers include a commissioning visit. Where they do, establish what it covers: making the final connection and testing it, or only witnessing and recording a connection made by others.

Ascertain whether the connection requires a licensed trade in the destination. In most markets the final electrical and gas connections do, and a supplier's technician who is not licensed there cannot make them, whatever the contract says. Confirm this before the unit ships, because it determines whether a licensed local contractor has to be booked into the delivery window.

Technician pressure-testing a plumbing manifold with a gauge and lever valves inside a plant cupboard
Pressure testing is carried out before the connection is closed up. The record of that test is what a later leak investigation starts from.

Step Three: Water Connection and Testing

The water scope is small and its failure mode is expensive, because a leak inside a finished envelope is discovered late and repaired destructively.

  • Confirm the supply characteristics available at the plot — connection type, available pressure and continuity — with the utility, before the unit is specified. A unit specified for a mains supply behaves differently on a pumped or stored supply.
  • Provide an isolator and a means of draining down at the entry, so that the unit can be isolated and drained without a visit to the street.
  • Make the connection at the designed entry position using the connector type the unit was built for, with the manufacturer's sealing method followed exactly.
  • Pressure test before closing up. Test the installation to the method and the level required by the applicable standard, and record the result. Do not cover the connection until it has passed.
  • Flush and disinfect the internal installation before handover where the applicable standard or the utility requires it, and retain the record.

Where the supply is intermittent or the pressure is variable, protection at the entry is a design item rather than an accessory. That is a question for the plot, and it is answered by whoever holds the site scope. Where the supply is a stored or rainwater source, treat the treatment and filtration requirement as a separate system with its own maintenance schedule.

Step Four: Drainage, Falls and Discharge

Drainage has one requirement that overrides every other consideration on this page: it has somewhere permitted to go.

  • Confirm the discharge route — a public sewer, an on-site treatment system, or a holding arrangement — and obtain its approval before the building approval if that is the local sequence.
  • Set the fall at the design stage. Waste drains by gravity. The fall is determined by the height of the unit's outlet relative to the discharge point, which means the substructure height and the invert level are decided together, not separately.
  • Provide access for clearance at every change of direction. A blocked run without an access point becomes an excavation.
  • Test the run to the method required by the applicable standard, and record it.
  • Keep surface water separate from the foul system unless the local authority permits a combined arrangement, because the two have different treatment destinations.

On a pier-supported unit this is straightforward. On a ground-bearing slab the outlet has to be formed through the slab at the right position, which is another reason the interface drawing matters at step one rather than at delivery.

Step Five: Electrical Supply and Earthing

This step is deliberately general, because the characteristics of the supply and the earthing arrangement are determined by the utility and the applicable standard in the destination, not by this page.

  • Establish what the utility will provide at the plot — the supply type, its capacity, and where the meter position will be — before the unit is specified. A unit built for a different supply arrangement is a modification, not a connection.
  • Have the earthing arrangement confirmed by a licensed electrician for that supply. Earthing practice is not uniform between markets, and it is a safety item.
  • Have the protective devices and any residual current protection selected and verified by the same licensed electrician, against the supply and the applicable standard.
  • Test and record the installation to the method required by the applicable standard, and retain the certificate where one is issued.

Do not accept a unit's internal electrical specification as evidence that it suits the destination supply. Confirm the match before production, because it is a modification at that stage and a rewire afterwards. Where a supplier states a compliance marking, request the certificate and confirm it with the issuing body. Requirements may vary by application, market and applicable standard.

Meter enclosure and earth electrode installed beside a modular building in daylight
Metering and earthing are provided for the destination supply. They are confirmed by a licensed electrician, not carried over from the factory.

Step Six: The Commissioning Record

The final step produces a document, and that document is what everything after handover is measured against. It should contain, at minimum:

  • The interface drawing as built, with any deviation recorded.
  • Water pressure test results and the date and method used.
  • Drainage test results for each run.
  • Electrical test results and the licensed electrician's certificate, where one is issued.
  • Confirmation that the isolators, the means of draining down and the access points are where they should be and are operable.
  • The identity and licence reference of every trade that made a connection.

Retain it with the unit. On a subsequent sale, a claim, or a relocation, the absence of this record costs more than the connection did. Where the unit is one of several on a site, keep the records per unit rather than per project, because the units will not stay together.

What to Confirm Before the Unit Ships

Closing this list before production is the whole value of the sequence:

  • Service entry positions agreed in writing on an interface drawing.
  • Supply characteristics and discharge route confirmed with the utility and the authority.
  • Responsibility for each connection allocated among the utility, the site contractor and the supplier.
  • Licensed trades booked into the delivery window where the destination requires them.
  • Commissioning scope stated, and the record format agreed.

None of these are optional, and none of them can be completed after the unit has been delivered. Requirements may vary by application, market and applicable standard.